Builder demanding extra ₹3 lakh before flat handover, is this legal?
I booked a 2BHK flat in a new construction in Pune and paid the full amount as per the agreement. Now, the builder is demanding an additional ₹3 lakh, claiming 'increased construction costs' before handing over the keys. I feel cheated and don't know if this demand is legal. Is there any legal action I can take against this? Should I report this to RERA or file a complaint in a consumer court? I am stressed about losing my savings and the flat.
Disclaimer: The answers on this page are for general informational purposes only and do not constitute legal advice. They do not create a lawyer-client relationship. Laws vary by jurisdiction and facts matter — please consult a qualified lawyer before acting on any information here.
- Review Your Agreement: Check the agreement for any clauses that allow the builder to increase the cost. Most agreements should have a fixed price unless there are specific provisions for escalation.
- RERA Complaint: If there is no such clause or if you believe the demand is unjustified, you can file a complaint with the Maharashtra Real Estate Regulatory Authority. RERA is designed to protect homebuyers and can order the builder to comply with the original terms.
- Consumer Court: You can also file a complaint with the Consumer Protection Act, 2019. This Act allows you to seek redressal for unfair trade practices and deficiency in service. The National Consumer Disputes Redressal Commission, in Fortune Infrastructure (NCDRC, 2014), held that builders cannot demand more than what is agreed upon without a valid reason.
- Legal Notice: Before initiating any formal proceedings, consider sending a legal notice to the builder demanding compliance with the original agreement. Sometimes, this can prompt the builder to retract the demand without further legal action.
It is indeed distressing to face such a situation. Let's address your concerns step by step.
First and foremost, the legality of the builder's demand for an additional ₹3 lakh depends on the terms of your agreement. You should review the Agreement for Sale you signed with the builder. Check if there is any clause that allows the builder to demand extra payment due to increased construction costs. If there is no such clause, the builder's demand is likely unjustified.
Given that your flat is in Pune, which falls under the jurisdiction of the Maharashtra Real Estate Regulatory Authority (MahaRERA), you can indeed report this issue to RERA. Builders are required to register their projects under RERA, and they must adhere to the terms agreed upon in the registered agreement. Any deviation without your consent can be challenged.
Here’s what you can do:
- Check RERA Registration: Verify if the project is registered with MahaRERA. You can do this on the MahaRERA website.
- File a Complaint with RERA: If the project is registered, you can file a complaint online with MahaRERA against the builder for demanding additional charges without justification.
- Consumer Court: If you wish to pursue a parallel remedy, you can file a complaint in the Consumer Forum. Under the Consumer Protection Act, 2019, demanding extra money without basis can be considered an unfair trade practice.
For legal precedents, you may refer to the case of Pioneer Urban Land and Infrastructure Ltd vs Govindan Raghavan (2019), where the Supreme Court held that the terms of the agreement are binding, and any unilateral demand by the builder is not permissible.
Additionally, you should act promptly as there are limitation periods for filing complaints. For RERA, it is advisable to file the complaint as soon as possible to avoid any procedural delays. For consumer complaints, the limitation period is generally two years from the date of the cause of action.
To summarize, you should review your agreement, check the project’s RERA registration, and consider filing a complaint with both RERA and the Consumer Forum. Taking these steps will help protect your rights and savings.